Find out dry material Required for 1cum. Cement Concrete 1:4:8 Ratio in Foundation.

Required dry material for 1 cum. Cement Concrete 1:4:8 Ratio in Foundation.

Solution:-

Ratio = 1:4:8 (Cement, Sand, Aggregates)
Sum = 1+4+8 = 13
Total Dry Mortar for 1 cum Cement Concrete = 1.54 cum.

Note.
VOLUME OF CEMENT BAG IN CUBIC FEET (CFT)since, 1 m³ = 35.3147 cubic feet = 28.80 No. of bags∴ Volume of one cement bag = 35.3147/28.80 = 1.226 CFT (cubic feet)
Therefor the Following Materials are Required:-

Cement = 1 x 1.54 x 28.8 / 13 = 3.31 Bags
Sand     = 4 x 1.54 / 13 = 0.47 cum.
Aggregates = 8 x 1.54 / 13 = 0.94 cum.

Cement =  3.31 Bags 
Sand     = 0.47 cum.
Aggregates = 0.94 cum.
Required dry material for 1 cum. Cement Concrete 1:4:8 Ratio in Foundation.

Comments

Popular posts from this blog

Medlum Density Fibre Board (MDF)

Medium Density Fibre Board (MDF)  MDF IS made from wood and other lignocellulose material refined into fibres and reconstituted with a resin binder. Row wood material is normally a single species wood. MDF has homogeneous structure with uniform density, texture and properties throughout, no identifiable grain can be seen at edge, end or face. There are no internal voids or pits and there is no variation in the surface hardness. Unlike plywood MDF doesn't delaminate. It has much higher strength than particle board. Since edges are totally smooth and uniform, costly tipping or beading with strips of wood required for plywood and particle board is not essential. It can be carved, grooved or embossed just like any timber. The surface of MDF is totally smooth and accepts all kinds of finishes - paints, varnishes and laminates. One such type of famous board in the market is 'Duratuff" . It comes in both interior and exterior grade. Duratuff prelaminated boards are also avail...

Construction Stages

                                                                            Construction Stages 1.       Excavation a.       9” brick work=3’X3’ (assumed at 3’-0” level we will get hard soil) b.       4.5” brick work=2’-6”X2’-6” c.       Columns= as per structural drawing, should be atleast 4’-6” down 2.       Termite treatment a.       Bayer’s premises b.       Biflex TC 3.       P.C.C. or Red Brick Ballast (4”-5” thick), stone aggregate is recommended 4.       Brick Work a.       9” wall= 27”,22.5”,18”,13” then plinth beam 9” thick then 9” brick work b....

Crank Details

Crank Length: -   Crank length is provided in Slab Shear stress is maximum at supports in Slab. So, to resist this stress we usually crank the bars at the ends of supports in slab,  Crank bar is bent up at an angle of 45 degree  with the length of 0.42 D  D = Depth of Slab-Top Cover-Bottom cover Crank is a slight bending in bars at the lap so that maintains the clear cover even at the lap position.The rule that is generally practiced is that the slope of crank 1:10 & minimum length of crank 300 mm. Formula of Crank length = (d1+d2+5)*10mm d1 =diameter of smaller bar d2 = diameter of largest bar क्रैंक लंबाई: - स्लैब शीयर में क्रैंक की लंबाई प्रदान की जाती है, स्लैब में समर्थन अधिकतम होता है। इसलिए, इस तनाव का विरोध करने के लिए, हम आमतौर पर स्लैब में समर्थन के सिरों पर सलाखों को क्रैंक करते हैं, क्रैंक बार 45 डिग्री के कोण पर मुड़ा हुआ है 0.42 डी की लंबाई के साथ D = स्लैब-टॉप कवर-बॉटम कवर की गहराई क्रैंक लैप पर सलाखों में हल्का सा झुका होता है ताकि ...