How To Calculate Quantity of Blocks ?

How To Calculate Quantity of Blocks.

Volume of wall = L x B x H
                          = 6 x 0.152 x 3 = 2.736 cum.
Volume of One Block Without Mortar = 0.405 x 0.152 x 0.200 = 0.012312 cum.
Volume of One Block With Mortar = 0.430 x 0.152 x 0.225 = 0.014706 cum.
No of Blocks =  Volume of Wall / Volume of One Block With Mortar
                       = 2.736 / 0.014706 = 186 Nos Blocks
Volume of Total Blocks = No's of Blocks X Volume of One Block Without Mortar
                                          = 186 x 0.012312 = 2.290032 cum.    
Volume of Mortar = Total Volume - Volume of Blocks
Wet Volume = 2.736 - 2.290032 = 0.445968 cum.
Dry Volume = Wet Volume X 1.27
                      = 0.445968 x 1.27 = 0.56637936 cum

Cement Mortar Ratio = 1:6 Ratio
Cement = Ratio of Cement X Dry Volume / Sum of Ratio
             = 1 x 0.56637936 / 7 = 0.08091134 cum.
Bags = 0.08091134/0.035 = 2.31 Bags
Sand = 6 x 0.56637936 / 7 = 0.48546802 cum.
Say = 0.5 cum.

How To Calculate Quantity of Blocks.

How To Calculate Quantity of Blocks.



Comments

Popular posts from this blog

The loads Acting on staircase.

Distribution of  Loads  and its Effect on  Staircase Stair  slabs are usually designed to resist gravity  loads , comprising of dead  loads  and live  loads  as described below:  1) Dead  Load : The components of the dead  load  to be considered are: a) Self-weight of  stair  slab (tread/tread-riser slab/waist slab) b) Self-weight of ... LIVE LOADS:- IS 875 parts II specifies the load to be considered as UDL of intensity 5KN/m2 for public  buildings and 3kN/m2 for residential building where the specified floor do not exceed 2kN/m2 and the staircases are should not liable for overcrowding. DEAD LOADS:- Self-weight of stair slab which includes the waist slab, tread-rise,etc. Self-weight of finishes (0.5 to 1 kN/m?) Types of stairs                                                ...

Construction Stages

                                                                            Construction Stages 1.       Excavation a.       9” brick work=3’X3’ (assumed at 3’-0” level we will get hard soil) b.       4.5” brick work=2’-6”X2’-6” c.       Columns= as per structural drawing, should be atleast 4’-6” down 2.       Termite treatment a.       Bayer’s premises b.       Biflex TC 3.       P.C.C. or Red Brick Ballast (4”-5” thick), stone aggregate is recommended 4.       Brick Work a.       9” wall= 27”,22.5”,18”,13” then plinth beam 9” thick then 9” brick work b....

How many Cement Bags Required for 200 Sq.ft Concrete Slab.

C ement Bags Required for 200 Sq.ft Concrete Slab. Concrete Slab area = 200 Sq.ft Assume Depth of Slab = 200 mm                                                = 0.2 m                                                                             = 0.65 ft.  Volume of Slab = 200 X 0.65 = 130 cu.ft  Cement content (as per IS) Min. Cement Content = 320 kg/cu.m  Max. Cement Content = 450 kg/cu.m 1 cu.m = 35.3 cu.ft  128 cu.ft = 130/35.3 = 3.682 cu.m  : Taking 400 kg/cu.m as Cement Content Casually Taken  Total Cement Content  = 400 X 3.682 = 1472.8 kg.  1 Bag Cement Wt. is 50 kg 1472.8 / 50 = 29.456 Bags   Ap...